CIG Construction / Project 04
Industrial estate refurbishment, Frome
Sixteen occupied industrial units re-roofed, repaired and brought back into good order for their local-authority landlord.
- Location
- Frome
- Sector
- Commercial (industrial units)
- CIG role
- Main contractor
- Programme
- January 2025, 5 months
The project
Industrial estate refurbishment,
Frome
CIG Construction refurbished an occupied industrial estate of sixteen units in Frome for its local-authority landlord. The metal roofs were cleaned, primed and overcoated with a warranted liquid waterproofing system, with cladding, rooflights and gutters repaired.
Roller shutter doors were replaced, party walls upgraded and vacant units fitted out, alongside drainage and tarmac repairs. Work moved terrace by terrace so tenants could keep trading.

In the detail
Roofs renewed over trading units.
The roofing manufacturer inspected preparation and coating thickness at each stage, so the twenty-year product warranty could be issued on completion.
Enlarge this detailThe project, in pictures
Other perspectives.
The finished work and the detail behind it. Select a photograph to explore.




CIG scope
The package
behind the pictures.
- Roof overcoating with a warranted liquid waterproofing system to sixteen units
- Cladding repairs, rooflights and rainwater goods
- Roller shutter door replacements
- Party wall upgrades and fit-out of vacant units
- Drainage and tarmac repairs across the site